A timber fire door only performs as tested if it is fitted to the manufacturer's certification, and a lot of doors in Bromley's houses, converted flats and commercial buildings are not. This guide covers what to specify, what good installation looks like and what records you should get at the end, whether you are replacing one door or a whole block's worth.
FD30 and FD60 tell you how long the door is tested to hold back fire: 30 or 60 minutes. Most flat entrance doors, communal corridor doors and doors to rooms off a protected stair in a three storey house or loft conversion need FD30, usually with smoke seals (FD30S). FD60 normally goes where the fire strategy calls for it, such as some plant rooms, stores or doors between separate parts of a commercial building. Your fire risk assessment, building control or the building's fire strategy should confirm which rating each door needs.
Where you can, specify a complete certified doorset rather than a loose leaf hung in an old frame. A doorset is tested as a whole: leaf, frame, seals, hinges, glazing and closer. That makes it much easier to show the door will perform as tested. Many older Bromley conversions still have upgraded panel doors or leaves hung in original frames, and these often fail an inspection.
Most of the failures we see are installation faults, not faults in the door itself. A properly fitted timber fire door should meet these points, and the exact tolerances come from the manufacturer's installation instructions:
In blocks of flats, the flat entrance doors and communal doors keep each dwelling separate from the escape route. Building owners, landlords and managing agents usually need to be able to prove that these doors are suitable and maintained. In multi occupied residential buildings over 11 metres, the regulations require communal fire doors to be checked every three months and flat entrance doors at least once a year, as far as is reasonably practicable. Planned replacement and regular inspections are cheaper than reacting to findings one door at a time.
Main contractors and commercial clients have their own sequencing problems. The doors often go in after the partitions are finished, and the fire stopping around the frames gets missed. Agreeing who seals the frame to the wall, and who records it, saves remedial work later.
Price depends on the rating, the size, whether the door is glazed, the ironmongery, and whether the frame has to come out. As a rough guide, a standard internal FD30 timber doorset supplied and fitted in a house might run from several hundred pounds up to about £1,200. A flat entrance doorset with a security lock, a closer and smoke seals often costs more. FD60, glazed doorsets and non standard openings add to the cost, and so does making good walls after an old frame is removed.
Sometimes a door does not need replacing at all. If the leaf and frame are certified and sound, remedial work may do the job at a fraction of the cost: adjusting the leaf, replacing seals, correcting gaps or upgrading the closer and hinges. An honest survey should tell you which doors fall into which group.
When the work is finished you should get written records that you can show to a fire risk assessor, an insurer, a freeholder or building control. These should include the door certification or a reference to it, the rating of each door, its location, the ironmongery fitted, photographs and confirmation that the door was installed to the manufacturer's instructions. Without that evidence, a well fitted door is hard to prove compliant.
Usually not. A standard door does not become a certified fire door by adding seals, because its construction has never been tested. In some cases an existing certified door can be upgraded or repaired, and a survey will tell you whether that applies.
A single doorset in a house or flat usually takes most of a day, longer if the old frame is difficult to remove or the opening needs adjusting. A programme of communal doors in a block is normally phased to keep escape routes usable.
Generally only in certain situations, most commonly where a loft conversion creates a third storey and the doors onto the stair need to be FD30. Building control or your designer will confirm what your project requires.
Tell us what you've got, whether a single door, a block of flats or a commercial building, and we'll arrange a survey and give you a straight, written quote.
Tell us about the doors or the building and we'll come back to you with a straight answer.